STREETS DEPARTMENT ANNOUNCES SCHEDULE FOR EVENING STREET RESURFACING

Temporary Parking Restrictions Expected

Philadelphia – Streets Commissioner Carlton Williams announced today that night work will commence for milling and resurfacing activities in the Southwest Philadelphia area beginning Monday, April 16 at 7 p.m. Temporary parking restrictions are expected.  The work is expected to be completed by Friday, May 11.

 
Milling and roadway resurfacing work will be performed on the following streets:

Buist Avenue from 76th Street to Lindbergh Boulevard
Lindbergh Boulevard from 65th Street to 84th Street
Mario Lanza Boulevard from 86th Street to Lindbergh Boulevard

 
The street resurfacing effort will be completed in four separate phases – street milling, the adjustment of manhole covers & utility boxes, final resurfacing, and line striping work.  Milling work by the contractor will be performed between 7 p.m. and 5 a.m., and the duration is expected to be five nights.  Manhole and utility box adjustments will be scheduled during the day, between the hours of 7 a.m. and 4 p.m.
 
Final paving will occur between 7 p.m. and 5 a.m., and the duration is expected to be five nights.  Line striping work will be scheduled between the hours of 7 a.m. and 4 p.m. Temporary ‘No Parking’ signs will be posted in advance of each scheduled activity.  Motorists are advised to allow extra time when traveling around the work areas.
 
The work is being completed by James J. Anderson Construction Company, Inc. The project is being financed with 100% City Capital Budget Funds.
 
The Streets Department thanks citizens in advance for their patience and cooperation during this project.

 
###